Mr. DeChantal sent in a revised Time Extension Request <br /> letter indicating the following completion dates: <br /> • Handicap Parking Pavement Marking Symbols — <br /> October 23 <br /> • Stone Veneer Columns Installation — October 28 <br /> • Street Light Installation — November 26 <br /> • Metal Benches Delivery — November 26 <br /> • Mr. DeChantal requested a revised Substantial <br /> Completion date of October 15, 2014 and a revised <br /> Final Completion date of October 31, 2014. <br /> I explained to Mr. DeChantal that these dates did not meet <br /> the original Contract's definitions that he would have some <br /> work in 2015 and so Final Completion could not occur until <br /> then, and suggested he revise his request. <br /> As of November 2, 2014, we have not heard from Mr. <br /> DeChantal. <br /> Council Action Requested: I would recommend the City <br /> Council take the tabled Change Orders "off the table" and <br /> deny them - with the anticipation that you will be <br /> addressing a future request. <br />