on the record drawing and the pipe shall be considered for possible replacement <br /> or repair when any future connection is made to manhole 8. <br /> Item 3 — Constructing ditching around the northwest cul-de-sac <br /> It is acceptable to leave this area as presently constructed. Please note that as driveways are <br /> constructed, care shall be taken so that run-off does not pond against the edge of the pavement <br /> and create future erosion problems. <br /> Item 4 — Construct by-pass lane on County Road #112 <br /> 1. All power poles adjacent to the bypass lane need to be re-located to the right-of-way. <br /> 2. The by-pass lane has been striped. <br /> 3. A roadside ditch, while shallow, needs to be constructed along the bypass lane, as well as <br /> the ditch north of the bypass lane needs to be stabilized and turf established. <br /> 4. These items will be considered complete upon the approval of the Crow Wing County <br /> Highway Department. <br /> Item 5 — Remove and replace cracked concrete curb and gutter sections as noted <br /> The cracks in the concrete curb and gutter have been filled with the Sealtight Futura— 15. The <br /> City of Pequot Lakes will monitor these areas next spring to see how they perform after going <br /> through the freeze/thaw cycle. <br /> Item 6 — Remove and replace concrete curb and gutter north of CB -4 to provide positive <br /> drainage to the catch basin <br /> It was agreed that Car-Col will remove the concrete curb and gutter north and south of CB — 4 <br /> and replace such that there is positive drainage. Car-Col will also remove and replace concrete <br /> curb and gutter south of CB — 3 such that there is positive drainage to the catch basin. <br /> Item 8 - Install 15" GS apron and remove sediment from sump area (Trailside Loop Sta <br /> 0+28) <br /> It is acceptable to not require installation of the GS apron in lieu of the rip-rap apron that was <br /> installed. <br /> Item 11 — Construct rip-rap channel at station 10+00 left <br /> We requested that the area adjacent to Trailside Road east of the spillway be re-graded such that <br /> the shoulder slopes away from the bituminous. It was agreed to leave this area as graded until <br /> turf is established on the retention pond slopes adjacent to the roadway. Upon those slopes being <br /> stabilized the shoulder area will be re-graded to promote drainage off the bituminous and this <br /> area will be seeded or sod placed. <br /> Item 15 — Verify drainage on the northwest side of the south cul-de-sac (station 6+75) <br /> We have verified that the bituminous in the cul-de-sac drains to the catch basin. <br /> Miscellaneous Items <br /> The two newly planted trees that would ultimately obstruct the visibility of the project stop signs <br /> have been relocated. <br /> At the beginning of Paul Circle there is curb and gutter that needs to have earth placed behind it <br /> on both sides of the road. <br />