City of Pequot Lakes WIDSETH <br /> Maintenance Dept. Facility Addition SMITH <br /> Feasibility Study , <br /> Page 6 NOLTING <br /> Probable Project Construction Costs <br /> The financial impact of notations above summarized by the architect, civil engineer, structural engineer, <br /> mechanical engineer and electrical engineer are as indicated below. All items are estimated in today's dollars. <br /> No factor was applied for future inflation. Contractor's General Requirements, Overhead and Profit are <br /> included in the numbers below. <br /> Option 1 (Building Addition and Upgrades) <br /> Maintenance Upgrades/Remodel to Existing <br /> The estimate of probable construction costs listed below is based on the work required to upgrade the <br /> existing mechanical systems as well as combining the two existing holding tanks. Also included are the <br /> requested improvements to extend the far north floor drains to the west and construct a new divider wall <br /> to the underside of the existing structure between the existing northern Fire Department stalls and the <br /> southern Maintenance Department stalls. <br /> Architectural Items $26,000 <br /> Civil Items $35,000 <br /> Mechanical Items $110,000 <br /> Fire Suppression Items $70,000 <br /> Electrical Items $2,500 <br /> Structural Items $2,500 <br /> Sub-Total $246,000 <br /> Building Addition <br /> Construction shall include removal of a majority of the existing north exterior wall. Subsequent new <br /> construction shall consist of a 35'-0"x 80'-0"addition to the north of the parking garage portion of the <br /> existing building. The addition would include a 25'-0"bay for two vehicle/equipment parking spaces <br /> along with an office,accessible toilet and storage room. <br /> The addition would consist of a pre-engineered steel building like the existing building and include one <br /> 16'-0"x 14'-0"overhead door. The following is a square foot estimate of probable cost. <br /> Addition 2,800 sq.ft.x$100/sq.ft. =$280,000 <br /> New Salt Storage Shed(Stick Built Construction) 2,000 sq.ft.x$ 80/sq.ft. =$160,000* <br /> Sub-Total $440,000 <br /> *Includes demolition of existing salt storage shed. <br /> Upgrades/Remodel to Existing $246,000 <br /> Project Contingency(20%) $137,000 <br /> Total(Option 1) $823,000 <br /> Note: Due to the smaller scale and maintenance upgrades/remodeling factor of this project, costs typically run <br /> higher than a larger new construction project benefitting from the economy of scale. <br /> J'\01308-City Of Pequot Lakes\0130B0057-Maintenance Facility Addition And Salt Shed Study10130130057.000-Maintenance Facility Addition And Salt Shed Stu4Reports\Feasibility Study.Docx <br />