Proposed timeline <br /> All engineering work completed: 2/28/2023 <br /> Does community have site control? Yes -Prescriptive Site Control* <br /> If the community does not have site control,when will it be 12/31/2022 <br /> secured? <br /> All necessary permits obtained: 4/30/2023 <br /> Bid process begin: 5/30/2023 <br /> Award construction contract: 6/30/2023 <br /> Facility operational: 1/1/2024 <br /> All Construction(including turf restoration)complete: 12/31/2024 <br /> *The new forcemain will be placed next to existing forcemain,which has a prescriptive easement.A <br /> recorded Right of Way will be sought for funders,if required. <br /> 10 <br /> Page 19 of 72 <br />