V <br />Estimated Percentage of Job Completed: 40.4% <br />Is Contractor's Const. Progress on Schedule: Yes <br />CONTRACTOR'S CERTIFICATION: <br />The undersigned Contractor certifies that <br />to the best of their knowledge, information <br />and belief the work covered by this payment <br />estimate has been completed in accordance <br />with the contract documents, that all amounts <br />have been paid by the Contractor for work for <br />which previous payment estimates were issued <br />and payments received from the Omer, and that <br />current payment shown herein is now due. <br />CONTRACTOR: DeChental Excavating, LLC <br />BY: <br />Date: <br />APPROVED BY OWNER: City of Pequot Lakes <br />BY: <br />Date: <br />ENGINEER'S CERTIFICATION: <br />The undersigned certifies that the work has <br />been carefully inspected and to the best of <br />their knowledge and belief, the quantities <br />shown in this estimate are correct and the <br />work has been performed in accordance with <br />the contract documents. <br />ENGINEER: WIDSETH SMITH NOLTING <br />BY: <br />Michael Rude, P.E. <br />PAGE 2 oft <br />PARTIAL PAYMENT ESTIMATE <br />NUMBER 2 <br />Name of Contractor: DeChantal Excavating LLC <br />P.O. Box 315 <br />Brainerd MN 56401 <br />Name of Owner: City of Pequot Lakes <br />4638 County Road 11 <br />Pe not Lakes MN 56472 <br />Date of Completion: <br />Amount of Contract: <br />Dates of Estimate: <br />Original: Substantial - July 28, 2009 <br />Original: <br />$198,940.59 <br />From: May 26, 2009 <br />Final - August 31, 2009 <br />Revised: Substantial - Au ust 21 2008 1, a] Sept be 18 200 <br />Revlsed: <br />$217,257.61 Chance Order #1 and #2 <br />To: June 18 2009 <br />Description of Project: 2009 South Oak Street Improvements <br />WSN No. 0130SO040 <br />CONTRACT ITEMS <br />THIS PERIOD <br />TOTAL TO DATE <br />INO. M <br />I <br />TEM DESCRIPTION <br />CITY. I <br />UNIT I PRICE I AMOUNT <br />QTY. <br />I AMOUNT <br />OTY. I AMOUNT 1% COMPLETE <br />Estimated Percentage of Job Completed: 40.4% <br />Is Contractor's Const. Progress on Schedule: Yes <br />CONTRACTOR'S CERTIFICATION: <br />The undersigned Contractor certifies that <br />to the best of their knowledge, information <br />and belief the work covered by this payment <br />estimate has been completed in accordance <br />with the contract documents, that all amounts <br />have been paid by the Contractor for work for <br />which previous payment estimates were issued <br />and payments received from the Omer, and that <br />current payment shown herein is now due. <br />CONTRACTOR: DeChental Excavating, LLC <br />BY: <br />Date: <br />APPROVED BY OWNER: City of Pequot Lakes <br />BY: <br />Date: <br />ENGINEER'S CERTIFICATION: <br />The undersigned certifies that the work has <br />been carefully inspected and to the best of <br />their knowledge and belief, the quantities <br />shown in this estimate are correct and the <br />work has been performed in accordance with <br />the contract documents. <br />ENGINEER: WIDSETH SMITH NOLTING <br />BY: <br />Michael Rude, P.E. <br />PAGE 2 oft <br />