Laserfiche WebLink
AGENDA ITEM #9.3 <br /> e��y of <br /> Pequot <br /> Lakes— _ <br /> REPORT TO CITY COUNCIL <br /> Report Prepared by: Tim I3oule <br /> Date: March 6, 2018 <br /> 5ubiect: Maintenance Facility Project Upda.te <br /> Report: The following is an update of the ta.sks and timeline for the <br /> Maintena.nce Facility Project. <br /> • We are awaiting bond and insurance information from Boser Construction. <br /> • The pre-construction meeting has been scheduled for March 21�. <br /> • From March to May (when road restrictions are removed), shop drawings, <br /> ordering of materials, and preparation will occur. <br /> • Per the contract, Project completion is no later than the end of September. <br /> Council Action Requested: No Council action requested. <br />